Fort Lauderdale fixed its yellow water. Why is Delray Beach waiting until 2028?

Fort Lauderdale’s mayor says his city’s long-running yellow-water problem is over. Delray Beach has now started building its own replacement treatment plant—but customers are paying higher rates while the projected finish remains nearly two years away.

The short answer
  1. Delray has acted: construction on a replacement plant is underway.
  2. The existing lime-softening plant is more than 60 years old and does not remove all visible natural color.
  3. The City’s project site lists August 2028 as the projected completion date.
  4. The unanswered question is not whether Delray is doing anything. It is why modernization took this long and what customers should expect while they wait.

Fort Lauderdale created a new comparison

Fort Lauderdale opened the Prospect Lake Clean Water Center on October 15 after beginning a gradual supply transition in September. On October 30, the South Florida Sun Sentinel reported Mayor Dean Trantalis saying the city’s yellow-water problem was a thing of the past.

The two cities are not identical, and one plant cannot simply be copied into another utility. But Fort Lauderdale’s announcement changes the regional conversation: visible natural color is not an unavoidable feature of South Florida drinking water when a utility installs treatment designed to remove it.

Read the Fort Lauderdale plant update →

Delray Beach has started—but residents are still waiting

Delray Beach officially broke ground on its new treatment plant on January 29, 2026. The City’s project website says construction is underway and identifies August 2028 as the projected completion date.

The project will replace the existing conventional lime-softening plant with enhanced treatment technology. The City says the current facility is more than 60 years old and that the replacement is needed to modernize infrastructure, improve water quality and meet future regulatory requirements.

Current plant

More than 60 years old and based on conventional lime softening.

Construction start

Official groundbreaking held January 29, 2026.

Projected completion

August 2028, according to the City’s project website.

Customer impact

Water and sewer rate increases took effect October 1, 2025 to help fund the project.

Why Delray water can still look yellow

Delray Beach draws groundwater from the East Coast Surficial Aquifer. The City explains that water picks up naturally occurring minerals and color as it moves through soil, sand, shell and rock. The existing treatment process removes as much natural color as it can, but a light-yellow tint may remain.

That explanation does not mean the City is intentionally adding color, and color alone is not evidence that the water violates a health standard. It does mean residents have lived for years with a visible condition that modern treatment is intended to improve.

Yellow does not automatically mean unsafe.

Appearance is an aesthetic indicator, not a complete safety test. A sudden dark-yellow, orange or brown change, particles, pressure loss or unusual odor should still be reported to the utility and checked against current notices.

How did a necessary project become so expensive?

The project’s estimated price has increased sharply over time. The Coastal Star reported in February 2025 that the total estimate could reach approximately $280 million, compared with an earlier estimate of roughly $120 million a few years before. Delray’s 2025–2026 city-manager annual report was later reported as placing the project at roughly $287 million.

Those figures are estimates, not a final audited construction cost. They nevertheless create a legitimate accountability question: which changes came from inflation, expanded treatment requirements, design development, financing, delayed execution or other project decisions?

Customers began paying more before receiving the new plant

At its May 20, 2025 meeting, the City Commission approved Ordinance No. 15-25 increasing water and sewer rates effective October 1, 2025. The project site says the increases will help pay for the new plant and notes that, before 2022, water rates had not been increased for more than 15 years.

Deferring rate increases can feel attractive in the short term. It can also leave a utility with less accumulated funding when aging infrastructure finally requires a major replacement. The City should explain how the long period without increases affected the project’s timing, borrowing needs and ultimate customer cost.

The questions Delray Beach should answer

  1. When did the City first determine that the existing plant needed full replacement rather than continued rehabilitation?
  2. Why did the project take until 2026 to reach groundbreaking?
  3. What caused the estimated cost to rise from earlier figures to approximately $280–287 million?
  4. What measurable reduction in finished-water color should customers expect from the new plant?
  5. What treatment capability will the plant provide for PFAS and other emerging standards?
  6. What interim steps will the City take for customers who continue receiving visibly tinted water through 2028?
  7. What schedule and cost protections are in place to keep the project from slipping again?

Florida Tap Report intends to request answers from the City and will add its response—or document the absence of one—in a dated update.

The bottom line

It is no longer accurate to say Delray Beach is doing nothing. The replacement plant is under construction. But beginning construction after decades of visible color does not erase the public-interest questions surrounding the delay, the rising estimate and the additional wait.

Fort Lauderdale has now shown what residents notice when a city completes advanced treatment: the water leaving the plant can look materially clearer. Delray Beach residents deserve a precise explanation of when they will receive the same kind of improvement, what it will cost and how the City will measure whether the project delivered.

— DELRAY BEACH RESULTS

Separate appearance from safety.

Review Delray Beach’s reported water-quality results, then check current notices if the color changed suddenly.

Open the Delray Beach report →

Why does Delray Beach water have a yellow tint? →

Check current Palm Beach County water alerts →

Article status

Published October 30, 2026 · No corrections posted.

Florida Tap Report will append any substantive response received from the City of Delray Beach and clearly date the update.