FLORIDATAP REPORTLOCAL WATER DATA • CLEAR ANSWERSEscambia County alerts →

— ECUA SYSTEM • PRECAUTIONARY BOIL-WATER NOTICE

ECUA lifts all hurricane-related boil-water notices

ECUA lifted all remaining hurricane-related precautionary boil-water notices October 15. Mainland Escambia County, Perdido Key and Pensacola Beach are cleared of the storm notices. The separate Bayou Boulevard notice was lifted October 16. Beulah–Helms and Marjean-area notices were lifted October 18. ECUA lifted the listed Old Spanish Trail addresses October 21 and the West Gregory and Mallory notices October 22. The separate River Road notice remains active. NPS’s October 18 Fort Pickens release separately retains a park water warning; see the park instructions below.

The short answer
  1. ECUA’s final hurricane-related rescission was updated October 15 at 11:30 a.m.; the issuer does not display a time zone.
  2. All remaining mainland storm exceptions, Perdido Key and Pensacola Beach are cleared of the hurricane notices.
  3. The separate Bayou Boulevard notice was lifted October 16 at 10:15 a.m.; Beulah–Helms and Marjean-area notices were lifted October 18. ECUA lifted the listed Old Spanish Trail addresses October 21 and the West Gregory and Mallory notices October 22. The separate River Road notice remains active.
  4. Check the exact addresses in ECUA’s current advisories before changing precautions.

What changed October 22?

ECUA lifted the October 20 West Gregory Street notice at 9:45 a.m. and the October 19 Mallory Street-area notice at 8:24 a.m. after satisfactory bacteriological surveys. The issuer does not display a time zone. Each lift covers its explicit address list. The separate 14100–14530 River Road notice remains active.

Read the West Gregory lift list and read the Mallory-area lift list. Both also appear on the current AlertCenter.

What changed October 20–21?

At 9:10 a.m. October 21, ECUA lifted the October 18 notice for 8480–8496 Old Spanish Trail Road and The Moorings Apartments at 8491 after satisfactory bacteriological testing. The lift’s explicit range differs from the earlier 8430–8496 issuance range. We have not extended that clearance to addresses absent from the lift; customers outside its list should confirm their instructions with ECUA. The issuer does not display a time zone.

Separate precautionary notices followed October 20 outages: 14100–14530 River Road, approximately 100 or more customers, issued at 8:10 p.m.; and 1701–2019 W. Gregory Street, between K Street and Pace Boulevard, approximately 40 or more customers, issued at 6 p.m. Service is restored, but the notices remain pending satisfactory sampling. A typical 48-hour test period is not an automatic lift. Check the current Escambia alert entries and official links.

What changed October 19?

ECUA issued a new localized precautionary boil-water notice at 6 p.m. after an unplanned outage near 3308 E. Mallory Street. The issuer does not display a time zone. It covers 3002–3008 E. Mallory Street; 1201 Scenic Highway; 1270 Van Kirk Avenue; 1207 Watson Avenue; 1270, 1275, 1300 and 1305 Pickens Avenue; and 1216 and 1300 Bayou Boulevard, affecting approximately 50 or more customers. ECUA subsequently lifted these listed addresses October 22 after satisfactory testing. This new notice is separate from the October 16 Bayou-area rescission.

Read ECUA’s October 19 Mallory Street-area notice and exact address list ↗

What does the Park Service say about Fort Pickens?

The National Park Service’s October 18 reopening release says the Fort Pickens Area reopened for day use at 9 a.m. while remaining under a boil-water notice. The Fort Pickens Campground and Battery Worth pavilion remain closed in that release. Its exact publication time and time zone are not displayed.

This is the park’s site-specific instruction. ECUA’s October 15 hurricane rescission does not establish clearance for the park notice described by NPS three days later. A separate park rescission was not verified when checked October 19. Visitors should bring bottled drinking water and check current NPS instructions before using park tap water.

What changed October 18?

At 3:20 p.m., ECUA issued a new precautionary notice for 8430–8496 Old Spanish Trail, including The Moorings Apartments at 8491 Old Spanish Trail, affecting approximately 50 or more customers after an unplanned outage. That issuance followed repairs and service restoration. ECUA subsequently lifted the explicit addresses listed in its October 21 notice; see the current scope above. The issuer does not display a time zone.

ECUA separately lifted the Beulah–Helms notice at 3:35 p.m. and the Marjean-area notice at 3:39 p.m. after satisfactory bacteriological surveys. The detailed notices and current AlertCenter confirm all three changes. Those October 18 lifts cleared their own listed areas only. Old Spanish Trail received its separate, explicitly scoped lift October 21.

What changed October 16?

ECUA lifted the separate October 14 Bayou Boulevard-area notice at 10:15 a.m. after satisfactory bacteriological testing. Its rescission lists the exact cleared addresses; the current advisory list and emergency banner also display the lift. The issuer does not display a time zone. Beulah–Helms and Marjean-area notices were separately lifted October 18. The October 21 Old Spanish Trail lift now lists 8480–8496 and The Moorings Apartments; follow the exact current scope.

What changed October 15?

ECUA’s AlertCenter and News Flash both confirm that all hurricane-related notices were lifted in its October 15 update at 11:30 a.m. This final lift supersedes the older mainland exception lists below. It covers the storm notices only.

The separate Bayou Boulevard notice was revised October 15 at 4:00 p.m., including 2905–3006 E. Moreno Street and 3002–3308 Mallory Street. At 8:45 p.m., ECUA posted separate precautionary notices for the listed Beulah–Helms and Marjean areas after unrelated outages and service restoration. These notice times do not display a time zone. The Bayou Boulevard notice was subsequently lifted October 16; ECUA subsequently cleared the Beulah–Helms and Marjean notices October 18.

What changed October 14?

ECUA posted its Pensacola Beach rescission October 14 at 9:00 a.m.; the page does not identify a time zone. The utility’s AlertCenter and News Flash both confirm the lift. Previously affected Beach customers may resume normal use under ECUA’s guidance. The remaining mainland storm exceptions were subsequently cleared October 15.

A separate notice posted October 14 at 6:43 p.m. covers approximately 100 or more customers near 1100 Bayou Boulevard. ECUA says that outage was unrelated to the hurricane. Read its original address list. ECUA subsequently lifted this separate notice October 16; the historical October 14 Beach rescission had not cleared it.

What changed October 13?

ECUA posted a partial rescission October 13 at 11:00 a.m. (the official page does not display a time zone). The utility lifted the precautionary notice for most mainland Escambia County and all of Perdido Key.

Pensacola Beach was still under notice at the time of the October 13 partial rescission. The official October 14 Beach lift above supersedes that status.

At the time, some mainland addresses remained under notice. Those storm exceptions were cleared by the October 15 final rescission. Read the utility’s final hurricane rescission; do not apply the storm lift to separate unrelated notices.

What changed Friday night?

Earlier Friday, ECUA's confirmed drinking-water impact was limited to the planned Pensacola Beach water and sewer shutdown. ECUA later issued a separate systemwide precautionary boil-water notice following the storm's impacts. That instruction applied systemwide at the time; the October 15 final hurricane rescission above now supersedes the storm notice.

ECUA's official notice was posted October 9 and made the advisory effective immediately. WEAR reported the notice at 7:38 p.m. CDT.

What changed late Friday?

At 11 p.m. CDT Friday, ECUA said it had begun the initial process of restoring water service. Crews were coordinating with debris-clearing teams to reach wells, inspect water-system infrastructure and identify needed repairs throughout Escambia County.

The update did not identify restored neighborhoods, give a completion time or lift the systemwide boil-water notice. Customers should not treat normal pressure or the start of restoration work as an all-clear.

What changed Saturday morning?

At 7 a.m. CDT Saturday, ECUA said water service had been restored to Baptist Hospital, Ascension Sacred Heart and HCA Florida West Hospital. The utility continued working with debris-clearing crews to reach water wells, assess damage and make repairs elsewhere.

The hospital restorations did not lift or narrow the notice at that time. The October 15 final hurricane rescission above supersedes the storm notice.

What changed Saturday afternoon?

At 1:43 p.m. CDT Saturday, ECUA said approximately 15% of its water services remained offline. Power outages, blocked roads, uprooted trees and other storm conditions were still delaying access and restoration in some areas.

ECUA also confirmed water service at the Escambia County Jail and Sheriff's Office, all three local hospitals, fire departments and the Pensacola Police Department. The utility said it expected a further update about its Water Quality Laboratory's ability to collect and process samples. The systemwide boil-water notice remained active.

What changed Saturday night?

At 8:40 p.m. CDT Saturday, ECUA posted a separate precautionary notice after completing initial post-hurricane assessment, repairs and flushing. The utility revised the notice at 8:49 p.m. to add the Lillian Highway segment. The October 10 notice covered the following areas; the October 15 final rescission later cleared all hurricane-related notices:

ECUA said bacteriological sampling had begun and the named areas would be lifted as they cleared. This new targeted notice does not by itself rescind the earlier systemwide notice: ECUA's active-advisory page continued to display both notices early Sunday.

When did service stop?

ECUA's original notice scheduled the shutdown for 3 p.m. Central time after first responders evacuated Pensacola Beach. A later October 9 update moved the shutdown up and said water and sewer service was being shut down immediately at approximately 2:30 p.m. CDT.

The utility announced the action after an evacuation order was issued for Pensacola Beach as Hurricane Isaias approached the northern Gulf Coast. The National Weather Service warned that damaging winds, storm surge, flooding rain and tornadoes could affect the region Friday into Saturday.

Why shut down both systems?

ECUA gave three operational reasons:

When can customers return to normal tap-water use?

Customers covered by ECUA’s final October 15 hurricane rescission may resume normal use under its instructions. Customers covered by the separate October 16 Bayou Boulevard rescission may also resume normal use under ECUA’s instructions. Customers covered by the October 18 Beulah–Helms and Marjean rescissions may also resume normal use under ECUA’s instructions. The October 21 Old Spanish Trail lift clears its listed addresses. West Gregory and Mallory were lifted October 22; River Road remains active.

Customers still covered by an active ECUA notice should continue following its instructions until ECUA clears their location. Fort Pickens visitors should follow the Park Service’s separate October 18 instruction above until NPS confirms the park’s status.

Is contamination confirmed?

No confirmed contamination was announced. ECUA describes the notice as precautionary following the hurricane. A precautionary notice means customers should use the protective instructions while the utility evaluates and clears the system; it is not proof that contamination was found at every tap.

What should customers still under notice do now?

  1. Use bottled or boiled water. Bring tap water to a rolling boil for at least one minute and allow it to cool before uses that could result in ingestion.
  2. Discard existing ice. Do not use ice made from water that was not boiled or otherwise confirmed safe under ECUA's instructions.
  3. Keep following the notice. Normal pressure, appearance or odor does not cancel the advisory; wait for ECUA's official rescission.
  4. Check for a separate notice. The hurricane lift did not clear unrelated notices. Bayou Boulevard was lifted separately October 16; Beulah–Helms and Marjean were lifted October 18. West Gregory and Mallory were lifted October 22. Follow the separate River Road notice if your address is listed.

Check current Escambia County water alerts →

Read the Florida hurricane tap-water guide →

Article status

Updated October 22, 2026 to record the West Gregory and Mallory rescissions and retain River Road’s separate active status. The previous update added NPS’s October 18 Fort Pickens reopening and continuing water warning, after verifying the Old Spanish Trail notice and the Beulah–Helms and Marjean rescissions on ECUA’s detailed notices and current AlertCenter. The October 21 update records the exact Old Spanish Trail lift list and the separate October 20 River Road and West Gregory notices, verified on detailed notices and the current AlertCenter. The October 15 final hurricane rescission remains in effect.

ECUA’s hurricane-related notices are lifted. NPS’s October 18 release separately retains a Fort Pickens park notice; no later park rescission was verified. Bayou Boulevard, Beulah–Helms and Marjean-area notices are lifted; the October 21 Old Spanish Trail lift clears its explicit list, while West Gregory and Mallory were lifted October 22 and River Road remains active. Follow each notice’s exact address list.

Sources

Fort Pickens notice reviewed October 19, 2026; ECUA notice dates remain identified above. Use the issuing utility or Park Service for current instructions.

Read our editorial and corrections standards →